Concrete Cracking > Concrete Breaking > Heathrow Airport


Client: Cappagh
Contract: Breakout


Webfell Minerals were awarded the contract for the concrete breakout at Heathrow Airport, Runway Rehabilitation & Block 115. Some 30,000m? of unreinforced P.Q concrete slab, ranging from 350mm to 450mm in depth, was broken out.

Sometimes known as rubblising, this enables the slab to be easily excavated, loaded into dumptrucks, taken to a primary crusher and then crushed to make a fill material, which then can be re-used on site.

The work was carried out with one Guillotine Breaker, with a 2.4m blade weighing 5.75 tonnes. This method is fast, clean and cost effective.

The concentration of breaking effort and energy ensures that debonding of concrete from reinforcement occurs, enabling both mesh and bar reinforcements to be removed relatively cleanly from broken concrete. This method of breakout is far quicker and more economical than any conventional methods.


< Back